Commercial Equipment & Machinery

TriMark's Musgrove Outlines Three Practices for Multi-Unit Equipment Rollouts

Three operational practices for equipping many locations at once: site-by-site playbooks, schedules built around manufacturer lead times, and deliveries consolidated per store.

Tamar AvetisyanNovember 1, 20265 min read3 views

Consolidated shipping cartons of small kitchen equipment staged beside a compact stainless prep table, with a countertop toaster, pans and serving scoops visible in an open box.

Bryan Musgrove, divisional senior director on national accounts at TriMark USA, has worked on many equipment rollouts built around new menu items. He points to three practices that make a multi-unit launch easier to execute.

Build a playbook for every location

TriMark worked with a brand that needed new toasters to add toasted sandwiches to a breakfast lineup already built on biscuits and wraps. The complication varies site by site: some locations have electrical capacity that is already maxed out, and small mall or urban units may lack the counter space for a toaster, forcing operators to create room with shelving or an additional table, which in turn affects workflow. A written playbook separates the locations that are plug-and-play from those that need extra support.

Schedule around the manufacturer's lead time

A manufacturer may be able to build 200 units, but the practical question is how long that takes. At 10 units a week, the run stretches to 20 weeks. A supplier might hold inventory for the first 50 units, then need eight weeks for parts sourced overseas before finishing the remainder. Where a menu item is tied to a marketing campaign for a specific season or occasion, the timeline should be constructed backward from the desired launch date so it stays achievable.

Repackage deliveries by location

Small wares are often shipped to stores in their original boxes. Musgrove suggests asking the dealer to consolidate them into one package per location instead. For one brand adding macaroni and cheese to its side lineup, the change required visual holding cabinets, pans and serving scoops in varying sizes; the items were combined into a single package per location, complete with instructional materials and exterior labeling so managers knew exactly what they were receiving on arrival.

Taken together — identifying which sites need more support, sequencing production realistically and simplifying deliveries — the practices are presented as a route to a smoother rollout. The stated aim is that, if the plan holds, the new menu item builds interest and brings in traffic.